国产精品久久77777 I 欧美激情精品久久久久久变态 I 久久久综合av I 亚洲色图第四色 I 国产精品无码AV I 男人的天堂色偷偷 I jizz亚洲女人高潮大叫 I 一本到免费视频 I 久久久精品久久久久 I 奇米777色 I 69久久久久 I 国产欧美视频一区二区三区 I 999在线精品 I 一区二区激情 I 日批网站在线观看 I 女生鸡鸡软件 I free性麻豆 I 欧美日韩国产网站 I 女人喷液视频 I 厨房掀开馊了裙子挺进 I 欧美中文字幕在线播放 I 亚洲精品久久久口爆吞精 I 视色视色影院视色影库视色网 I 欧美老年两性高潮 I 丈母娘的诱惑电影 I 91波多野吉衣 I 麻豆91在线看 I 女人被c爽视频免费看 I 性导航美国十次狠狠lu噜 I 狠狠色狠狠爱综合蜜芽五月 I 偷自拍亚洲综合在线 I porn麻豆 I 18av网站 I 自拍新婚之夜初交视频1 I 精品久久一二三 I 97久久精品人人 I 免费欧美裸体视频 I 午夜激情伦理 I 中文字幕av一区乱码

CN EN
Market News
National Energy Board will implement the new energy grid Deal
Time:2013-02-17

The new energy industry will usher in a new positive. "Renewable energy power priority access management approach" is being used by organizations to develop the National Energy Board, which will focus on ways to solve the power problem is difficult to purchase all the wind power and solar energy, etc. In addition, the industry's long-awaited "renewable energy quotas management approach "will also choose the introduction. 

In addition to the grid, the National Energy Board also amended to adjust the installed capacity target of "renewable energy" second five "plan" for solar power, up from 21 GW to 35 GW. 

Grid Deal 

Wind power and solar power has always been there and the difficult problem of network. 

SERC last August release of "key areas of wind power consumptive regulatory reporting," pointed out that the current national focus on the area of wind power "abandoned wind" is getting worse, where the north, northwest and northeast where the "Three North" region and net installed Although the capacity and power generation accounts for more than 85% of the country, but abandoned the year 2011 amounted to 12.3 billion kwh of wind power, electricity corresponding loss of about 6.6 billion yuan. 

Here, there are data that the current "Three North" region and the Inner Mongolia region and some wind farms have not been accepted or abandoned wind power reached 20%. 

Not only is wind, solar and net situation is not optimistic. A reporter recently acquired information and data, as of the first half of 2012, 2009 and 2010, Golden Sun project directory, the main project is completed and approved the project network project 106, the main project is not completed and the network project 44. 

From this perspective, grid projects accounted for 71% of completed projects, and network situation is more optimistic. However, sources close to the related statistics, told reporters that the grid project divided into two cases, one is an official with the State Grid and Project Network license file, there is no such document, but a business on their own projects and networks "But very few of the former, in accordance with the actual meaning of the grid, is to be accepted into the national grid and the grid system of electricity generation as circumstances permit, and no more than 10 projects, 90% or more of the project did not achieve real Grid sense. 

For reasons difficult and networks, a Bureau of Energy said that the presence of three main issues, namely market space problems, one is conveying path problem, but also a run and subsidies. "Take wind power, if developments in the case of existing power system is not changed, the industry market space utilization has been completed, if not make changes on the institutional mechanism, there would be no room for development of wind power, even change the pattern, as well as the southern point of space , also have developed over two years, so the market problem is the question of changing the institutional mechanisms. "these people said. 

In this regard, the sources said, this year's Energy Bureau plans to add wind power installed capacity of 18 million kilowatts, and in 2009-2012 the planning of new installed capacity is 15 million kilowatts, "the capacity of the previous plan is to start this year to is the result, look at the actual grid. "

According to the source, at present, the Northeast region, Inner Mongolia, northwest region, including North China's Zhangjiakou and Chengde transport corridor problem exists, "I will not speak to coordinate uncoordinated, these areas are not enough transmission capacity, we first have to solve the transmission bottleneck off. "